Found a story on the new consolidated school being built over in Harlan Co. for Cawood, Evarts & Cumberland (Harlan itself is independent, like Wise), that says they're now paying $157 per square foot, which is quite a bit below the Va. avg. of $184.
Let's split the diff. and say Wise gets quoted $170 psf. That's about 8% below the Va. avg., and reduces my guestimate of $79 Million for 3 new 9-12 schools and $72 Million for 2 new 9-12 schools by about $6 Mil. to 73 and 66.
http://www.harlandaily.com/articles/...s/news9080.txt
Also read an update on the Clarke Co. school building project. The Winchester Star story says "...construction costs are escalating 1 percent per month..." So, $70 mil. now would become $78.5 mil. in a year. Hope they hurry up and decide.
http://www.winchesterstar.com/TheWin...Area_delay.asp